Project Implementation Mechanism in Future


Seven years’ Project implementation shall be completed through the office of the Project Director to be established specifically for the purpose under the overall guidance and supervision of the Steering Committee constituted for the purpose.

Phase I: (2016-18)
The initial stage shall include induction of necessary human resource, training and orientation of project staff with the concept of Pak-Austria Fachhochschule: Institute of Applied Sciences & Technology (PAF-IAST) provision of necessary infrastructure and other facilities such as lab equipment, IT services, furniture/fixture, transportation etc.
Selection of 25 PhD's through proper procedure in the mentioned disciplines for induction in University of Haripur for upto 2 years training in each partner institutions.
With the completion of two state of the art purpose built infrastructure at campus, University of Haripur is having basic infrastructure to start its academic activities in fall 2017 session in line with project concept.
Phase II (2018-21)
During this phase, after receiving necessary funding under the proposed PC-1University of Haripur shall start infrastructure development for Pak-Austria Fachhochschule: Institute of Applied Sciences & Technology (PAF-IAST) campus. It is planned to complete the following structures during this phase:

  1. Two academic blocks
  2. One admin block
  3. Central Library
  4. Central Laboratory
  5. Video conferencing facilities
  6. One hostel each for boys and girls
  7. Faculty hostel

Establishment of state of the art, science, IT and digital media labs shall be completed during this phase.  HRD such as induction of highly qualified faculty/staff and their training shall be continued during this phase.
Establishment of Technology Park shall be initiated.

Phase III (2021-2023)
Third phase is the completion phase of the project. Infrastructure development will be completed. Construction of Technology Park as essential part of concept shall be accomplished during this phase. Induction of required faculty and staff for all programs and their training through faculty exchange program shall be continued till achieving desired level.